Loudoun County Supervisor: Finance/Government Operations And Economic Development Committee - Capital Improvement Program Work Session - Mar 05, 2025

View Video

Key Topics Discussed

  • πŸ•’ 00:07:31 Capital Improvement Program (CIP) Work Session: The committee discussed updates on the CIP, including responses to questions and proposed budget adjustments.
  • πŸ•’ 00:11:03 Fleetwood Road Study and Russell Branch Parkway Project: Supervisor Glass proposed motions regarding the study of Fleetwood Road and the removal of the Russell Branch Parkway project from future consideration.
  • πŸ•’ 00:16:30 Evergreen Mills Road Project and Route 287 Improvement: Chair Randall made a motion to reallocate funding from the Evergreen Mills Road project to the Route 287 and Eastgate Drive improvement project.

Decisions & Votes

  • βœ… Motion Passed: The committee approved Supervisor Glass's motion regarding the Fleetwood Road study and Russell Branch Parkway project with a vote of 3-0-1.
  • βœ… Motion Passed: The committee approved Chair Randall's motion to reallocate funding from the Evergreen Mills Road project to the Route 287 and Eastgate Drive improvement project with a vote of 4-0-1.
  • βœ… CIP Packet Motion Passed: The committee forwarded the amended CIP to the Board of Supervisors for review and approval with a vote of 4-0-1.

Notable Quotes

  • πŸ—£οΈ "I would like to abstain because I don't know this issue well enough to vote on it." – Supervisor Randall
  • πŸ—£οΈ "This is just for future years, so we're not impacting anything fiscally here." – Chair Briskman
  • πŸ—£οΈ "The linear parks and trails program, once called the Emerald Ribbon, is a magnificent feather in the cap of Parks and Rec and really involves the county." – MADAM Chair

Follow-up Actions

  • πŸ“Œ Review and Approval: The Board of Supervisors will review and approve the amended CIP on March 10th.
  • πŸ“Œ Budget Adjustment: Staff will execute a budget adjustment to move $250,000 from the Capital Project Management Account to a newly created Fleetwood Road Improvement Project.
  • πŸ“Œ Pedestrian Crossing Construction: Staff will appropriate $1.2 million to the Linear Parks and Trails Program project to construct a pedestrian crossing over Beaverdam Run.

Summary by Timestamp

  • 00:06:49: The meeting was called to order, and the committee began discussing the CIP work session.
  • 00:07:31: Staff provided updates on the CIP, including responses to questions and proposed budget adjustments.
  • 00:11:03: Supervisor Glass proposed motions regarding the Fleetwood Road study and Russell Branch Parkway project.
  • 00:16:30: Chair Randall made a motion to reallocate funding from the Evergreen Mills Road project to the Route 287 and Eastgate Drive improvement project.
  • 00:21:42: The committee discussed and voted on the CIP packet motion, which included forwarding the amended CIP to the Board of Supervisors for review and approval.
  • 00:27:11: The meeting was adjourned with no further business.
    Notice:
  • Summaries are AI Generated using AI generated subtitles.
  • As such, they may contain errors.
  • Review the original video for accuracy before you make any decision based on these summaries.